|
Frequently Asked Questions
(Technical) |
Here I am trying
to answer the doubts expressed by my colleagues, particularly many of the
juniors. I like to describe them here because, it could be helpful to others
too. More over, it will help me to refresh myself. |
|
|
|
Grading in between
switches/breakers |
|
Definition for High Rise Building [Multi Storied Building] |
|
Fire Pump to be counted for connected load? |
|
What is meant by Contract
Demand? |
|
With cable voltage drop
calculation, phase voltage drop or line voltage drop is to be assessed? |
|
1
Second fault clearing time of cable |
|
Switch pole specification
- SP SPN TP TPN |
|
Current density (A/Sq.mm) of earthing conductors |
|
Earth Fault &
Earth Leakage |
|
How the value of '20% of line current' is
reached for earth fault protection setting? |
|
MCB curves - B, C
& D |
|
Cable
Code as per IS:1554(Part1) & 7098(Part1) |
|
How
can we determine the capacitor required for an electrical installation, in
its design stage? |
|
Why
power factor improving capacitors need not be insisted for the V3f driven
Lift Motors? |
|
What
about the requirement of an additional secondary breaker for a transformer,
if cable length exceeds a limit? |
|
Is it necessary to
have UV coil tripping facility to the grid side of a switch board, in which
generator supply is also fed through a change overing device? |
|
What is
Arc Fault Circuit Interrupter (AFCI)? |
|
Is it
necessary the Bus Coupler should have same current rating as that of the
incomer switch/breaker? |
|
Distinguish
between ELCB, RCCB & RCBO |
|
Galvanic isolation |
|
Explain about the provision of mechanical interlock and the lockable push button insisted, when a dry type transformer is installed above ground floor,
|
|
What is wrong in keeping power factor improving capacitors online,
while the power source is a generator and not the grid? |
|
What is the load limit insisted for HT-LT tariff? |
|
What are the voltage limits insisted for different connected loads? |
|
In case of multi storied building, what are the limits
insisting for provision of transformer? |
|
In case of multi storied building consumers, what is
the load limit for HT-LT tariff? |
|
Conditions to avail HT common supply in a high rise
apartment building may be explained. |
|
Explain
AVR (Automatic
Voltage Regulation) |
|
In which cases the outdoor transformer
installations are restricted? Also, in which cases the oil type
transformer installations are restricted? |
|
Why transformers are rated in kVA? |
|
What is the condition to have light
circuit segregation in factory premises? |
|
How
to calculate the voltage drop of a 3 run cable, say 3Rx3.5x185 Sq.mm
cable? |
|
What is
RTCC? |
|
Percentage
Impedance - basics |
|
Why
voltage multiples of 11 is preferred? (eg:-
11kV,
110kV, 220kV, etc.) |
|
Conductivity of Metals |
|
I shall
answer the following questions soon. If you have an urgency to get a
reply, please Email me. |
|
What is
the limit of transformer rating in pole type constructions? |
|
What is
the limit of transformer rating in 11kV/440V range? |
|
For
Lift or High Rise Building, is Generator mandatory? |
|
What
about the al-round clearance required for a dry type transformer
placed along with the panels in an electrical room? |
|
Is
hinged door mandatory for Acoustic Chambers? |
|
What about Foundation Earth Electrodes to
consider instead of the conventional earthing methods for an
electrical installation? |
|
How
much the value of Fault Level of a 33kV substation in Kerala
to be taken? |
|
How
to decide the 11kV side fuse of a Distribution Transformer? |
|
Is it
mandatory to have Electrical Duct for a Multi Storied Building? Why
can't use external Electrical Tray? |
|
|
|
Please join the Technical Discussions at the
Forum - Click here |
|
Top |
|
|
Grading in between
switches/breakers |
|
(i) When ACB is
provided as the incomer of a switch board, the outlet switch (not for breaker) rating shall not
be less than 1/3rd of the incomer current setting. [If the outlet device is a
breaker, this grading need not be applied, since the breaker is having
breaking capacity, where as switch doesn't have it.]
(ii) When MCCB is
provided as the incomer of a switch board, the outlet switch (not for breaker) rating shall not
be less than 1/5th of the incomer current setting.
(iii) When ACB/MCCB
is provided as the incomer of a switch board, the outgoing fuse rating shall
not exceed 1/3rd of the incomer current setting.
(iv) When ACB is
provided as the incomer of a switch board, the outlet MCCB can be set up to
80% of the incomer current setting.
(v) When MCCB is
provided as the incomer of a switch board, the outlet MCCB can be set up to
50% of the incomer current setting.
(vi) When switch fuse act as the
incomer of a switch board, the outlet switch rating shall not be less than
1/10th of the incomer fuse rating. Also, the outlet fuse shall not be greater
than 1/2 of the incomer fuse rating.
|
|
Back |
|
Definition for High Rise Building [Multi Storied Building] |
|
The
Indian statutes are defining a Multistoried Building/High Rise Buildings as
a building having a height of more than 15m. The height is defined to
measure from the average street level to the plinth level of the terrace.
When there are two approach roads in different levels, the height shall be
measured from the highest level, if fire engine access is there. |
|
Back |
|
Fire Pump to be counted for connected load? |
|
Load of fire protection
equipment shall not be considered for assessing the connected load if the
same is connected to standby generator. |
|
Back |
|
What is meant by Contract
Demand? |
|
Contract Demand means the
maximum Demand in kVA mentioned in the agreement between the supplier and
the consumer. In case of HT and EHT connections, the contract demand shall
be treated as the connected load. |
|
Back |
|
With cable voltage drop
calculation, phase voltage drop or line voltage drop is to be assessed? |
|
It is beyond doubt that in case
of single phase cable, phase voltage drop only is to be assessed. If the
cable is 4 cored, chance being there for single phase load, again phase
voltage drop is to be assessed. [Phase voltage drop will be higher than the
line voltage drop, hence better design]. In case the cable proposed is only
for 3 phase load, or otherwise if the cable is of 3 cored, only line voltage
drop need to be assessed. |
|
Back |
|
1
Second fault clearing time of cable |
|
The fault clearing
time is determined by the fault level and the time taken by the device
installed at the source to cut off the supply. In case we can manage to
limit the cut off time to 0.5 sec, definitely, we can go for smaller
sections. Under any condition, modern technological advancements ensure cut
off within 1 second. So it is safe to design with 1 second. |
|
Back |
|
Switch pole specification
-
SP SPN TP TPN |
|
SP � Single
Pole � No link/pole is provided for Neutral.
SPN � Single Pole Neutral Link � Two Poles, but for the Neutral Pole
a link is provided.
TP - Tripple Pole � No link/pole is provided for Neutral.
TPN � Tripple Pole Neutral Link � Four Poles, but for the Neutral
Pole a link is provided.
DP � Double Pole � Two Poles; one for Phase and the other for Neutral
FP � Four Pole � Four Poles; three poles for the three phases and
fourth for Neutral |
|
Back |
|
Current density (A/Sq.mm) of earthing conductors |
|
Fault clearing time |
Cu |
Al |
Steel (GI) |
|
|
1 Second |
205 |
126 |
80 |
|
|
3 Second |
118 |
73 |
46 |
|
|
For earth design,
fault clearing time is taken as 3 second. |
|
Back |
|
Earth Fault &
Earth Leakage |
|
An earth
fault is when the safety earth is either missing or high resistance.
Earth leakage is when either live or neutral is leaking to earth through a
bad insulator. |
|
Back |
|
How the value of
'20% of line current' is reached for earth fault protection setting? |
|
The
ratio of neutral CT for earth fault protection is selected based on
the sensitivity we need.
For
example consider a 5 A relay with plug set at 2A ( say ). ie. the
relay will operate when 2A current flow through the relay coil. Let
us consider different CT ratios for this relay. The minimum primary
current in CT for operating the relay will be as follows:
CT
ratio |
Minimum CT primary current to operate the relay at 2A plug
setting = 2 x CT ratio |
200 /
5A |
80 A |
100 /
5A |
40 A |
75 /
5A |
30 A |
50 / 5A |
20 A |
It
can be seen that , as the CT ratio becomes lower , the relay
operates at lesser current. ie. the sensitivity of the earth fault
system is improved when the CT ratio is lowered. Hence depending up
on the sensitivity we need we may select the corresponding CT ratio.
( This is similar to using 30 mA ELCB in light circuits and 100/300
mA ELCB in power circuits )
If no
specific sensitivity is required we take the CT ratio as 20 % of the
rated current of the equipment protected. It is an empirical value
based on practical experiences. It is recommended that the CT ratio
shall not be higher than this value. |
|
Back |
|
MCB curves - B, C
& D |
|
The
relationship between current and tripping time is usually shown as a curve,
known as the MCB's trip characteristic.
The most important curves are B, C and D.
Type B
MCBs react quickly to overloads, and are set to trip when the current
passing through them is between 3 and 4.5 times the normal full load
current. They are suitable for protecting incandescent lighting and
socket-outlet circuits in domestic and commercial environments (resistive
loads), where there is little risk of surges that could cause the MCB to
trip.
Type C
MCBs react more slowly, and are recommended for applications involving
inductive loads with high inrush currents, such as fluorescent lighting
installations. Type C MCBs are set to trip at between 5 and 10 times
the normal full load current.
Type D
MCBs are slower still, and are set to trip at between 10 and 20 times the
normal full load current. They are recommended only for circuits with very
high inrush currents, such as those feeding transformers and welding
machines. |
|
Back |
|
Cable
Code as per IS:1554(Part1) & 7098(Part1) |
|
'A' -
Alluminium
'2X'
- XLPE Insulation
'F' -
Steel Strip Armour
'y' -
PVC Insulation
'W' -
Steel Round Wire Armour
'y' -
PVC Outer Sheeth
'ww'
- Steel Double round wire armour
'yy'
- Steel Double Strip Armour
'Wa'
- Non Magnetic round wire armour
'Fa'
- Non Magnetic flat strip armour
'FF'
-Double
Steel; Round Wire Armoured
Note - No
code letter for conductor is required when the conductor material is copper.
eg:- AYFY -
Aluminum PVC Insulated Flat strip armour and PVC outer sheeth cable |
|
Back |
|
How
can we determine the capacitor required for an electrical installation, in
its design stage? |
|
If the power factor was known, we could
determine the capacitor rating as kW x [tanΦ1-tanΦ2],
to raise the power factor from cosΦ1
to cosΦ2.
Being in design stage, you may take an average power factor of 0.8, in place
of cosΦ1. |
|
Back |
|
Why
power factor improving capacitors need not be insisted for the V3f driven
Lift Motors? |
|
V3f
(Variable Voltage Variable Frequency) drive consists of 3 blocks. A diode
bridge rectifier gives DC supply to a Dynamic Braking Unit. Now
this DC supply is inverted to AC and fed to the Lift Motor. The power
factor to the AC line at the input side of the bridge rectifier is near to
unity. The output may have an inductive, or lagging, PF due to the motor's
inductive reactance. However, the motor's reactive current is circulated
between the motor and the inverter but not to the input line. Hence,
capacitor is not necessary for such variable speed drives for power factor
improvement. More over, the power factor improving capacitors connected to
the motor terminals may become overheated due to the potential high
frequency noise transmitted from inverter.
The V3F
drive results in good ride comfort with 50% energy savings compared to
single-speed elevators. The V3F drive will adjust and maintain the
rotational speed of the motor in accordance with the load and position of
the car relative to floor level. A motor mounted encoder can provide
velocity feedback to the V3F drive. Information from the encoder is used
with exact car position information from the leveling system to provide
accurate floor leveling. |
|
Back |
|
What
about the requirement of an additional secondary breaker for a transformer,
if cable length exceeds a limit? |
|
Previously we were
insisting to have an additional secondary breaker, if the secondary cable
length exceeds 15mtr. But now, we didn't have such an instruction. Still, it
is advisable to have an additional breaker, if the cable length exceeds a
reasonable limit, say 40mtr. The purpose of the breaker is for the secondary
cable protection. Usually, such cases come with factory installations. |
|
Back |
|
Is it necessary to
have UV coil tripping facility to the grid side of a switch board, in which
generator supply is also fed through a change overing device? |
|
There were many
accidents happened due to failure of the change overing mechanism, and
thereby back feeding of the stand by supply to the grid line. With most of
the standard AMF circuits, there will be under voltage tripping provision.
But, in many electronic change overs, there may not be adequate protection
to prevent this danger. Where as, with conventional change over switches
since no automatic change overing to happen, may not be insisted to add uv
tripping facility. But, it is your discretion, so as to ensure the
protection. |
|
Back |
|
What is Arc Fault Circuit Interrupter (AFCI)? |
|
Circuit
Breakers or Fuses in a circuit will detect an
unusually high current load and shut off the electric current when the
current exceeds a certain level. Today, circuit breakers are commonly used
compared with fuses, being simple to reset after they trip from a high
electrical load. But, circuit breakers can malfunction and do not always
shut off a high current. On the other hand, fuses almost always shut off the
current. The element inside them literally melts when the designated current
is exceeded. If you want to protect sensitive equipment, fuses are better
than circuit breakers. Earth Leakege Circuit Breakers (ELCB)
function differently. Their purpose is to detect a leakage current that can
allow electricity to pass through your body to ground.
The other type of
common electric problem that causes fires is an arc fault. This may be
caused by a loose wire at a switch, a break in the wire insulation where a
nail in the wall hit it, just old kinked wire insulation, etc. This arcing
or spark can ignite any combustible materials inside the wall. When arcing
occurs, the electrical current is not excessively high, so a standard
circuit breaker or fuse will not detect any problems. An ELCB will not
detect this problem either because the incoming and exiting currents are the
same. There are new types of circuit breakers that incorporate an additional
sensor to detect arcing. These are called arc fault circuit
interrupters or breakers (AFCI). Special electronic control
circuitry inside it detects the changes in the current flow that are
specific to arcing and it shuts off the current.
The AFCI circuitry
continuously monitors current flow through the AFCI. AFCIs use unique
current sensing circuitry to discriminate between normal and unwanted arcing
conditions. Once an unwanted arcing condition is detected, the control
circuitry in the AFCI trips the internal contacts, thus de-energizing the
power circuit and reducing the potential for a fire to occur. An AFCI should
not trip during normal arcing conditions, which can occur when a switch is
opened or a plug is pulled from a receptacle.
Presently, AFCIs
are designed into conventional circuit breakers combining traditional
overload and short-circuit protection with arc fault protection. AFCI
circuit breakers (AFCIs) have a test button and look similar to ELCBs. Some
designs combine ELCB and AFCI protection. Additional AFCI design
configurations are anticipated in the near future. |
|
Back |
|
Is it
necessary the Bus Coupler should have same current rating as that of the
incomer switch/breaker? |
|
The bus coupler
rating need to be same as that of the incomer switch/breaker, only if we
notice a chance to carry the same load through the bus portion. Otherwise,
why we need to insist so? To convince yourselves, just consider the bus
coupler as a sub circuit incomer and the bus portion as the sub switch
board. |
|
Back |
|
Distinguish between ELCB, RCCB & RCBO |
|
ELCB ( Earth
Leakage Circuit Breaker) is the basic terminology of the device to sense and
protect a circuit from earth leakage. There are two types of ELCBs; the
voltage operated device and the differential current operated device. The
differential current operated ELCB is termed as RCD ( Residual Current
Operated Device). RCCB (Residual Current Circuit Breaker)
is nothing but an RCD. But, literally still we have the tendency to use the
term ELCB instead of RCD or RCCB, though the terms have a slight difference.
So, I like to make you ascertain that the terms ELCB & RCCB represent the
same compared with the device
RCBO
(Residual Current Circuit Breaker with Overcurrent protection). which
combine the RCCB and MCB functions into one package.
Read More!. |
|
Back |
|
Galvanic isolation |
|
Galvanic isolation is the principle of isolating functional
sections of electric systems so that charge-carrying particles
cannot move from one section to another, i.e. there is no electric
current flowing directly from one section to the next. Energy and/or
information can still be exchanged between the sections by other
means, however, such as by capacitance, induction, electromagnetic
waves, optical, acoustic, or mechanical means. Galvanic isolation is
used in situations where two or more electric circuits must
communicate, but their grounds may be at different potentials. It is
an effective method of breaking ground loops by preventing unwanted
current from traveling between two units sharing a ground conductor.
Galvanic isolation is also used for safety considerations,
preventing accidental current from reaching the ground (the building floor) through a person's
body.
Read More!. |
|
Back |
|
Explain about the provision of mechanical interlock and the lockable push button
insisted, when a dry type transformer is installed
above ground floor. |
|
When the
dry type transformer is installed above ground floor, the 11kV
breaker is to be kept in ground floor itself. To ensure double
security, (i) a lockable push button incorporated with
the 11kV breaker shall be kept near the transformer and (ii) a
two lock - one key arranged mechanical interlock
shall be provided in between the transformer and the breaker
enclosures. Using the push button, we could isolate the 11kV supply
in case of emergency, from the neighbourhood of the transformer.
About the mechanical interlock, the key is inside the lock of the
11kV breaker to keep it in working condition. To open the
transformer enclosure, firstly the key is to be taken from the lock
of the 11kV breaker and put in the lock of the transformer
enclosure. To take out the key from the lock of the 11kV breaker, it
will be possible only after making the breaker off. Hence, the
transformer enclosure can be opened only after isolating the 11kV
breaker. Thereby, double security is ensured through this
arrangement. In such installations unitised substations are not
advisable, due to the additional requirement of an 11kV breaker in
ground floor. |
|
Back |
|
What is wrong in keeping power factor improving capacitors online,
while the power source is a generator and not the grid? |
|
Generators
are inherently capacitive. Let the generator starts, ofcourse at no
load. At this stage, if some additional leading current is
injected (by the provision of an external capacitor), it will add
voltage and hence the voltage control of the generator may get
damaged. Normally as per generator capability curve, the margin for
leading PF will be much less, when compared to lagging PF. So, we
need to ascertain that at the start or running stages of the
generator, causes for a leading PF should not be encouraged.
Generally
speaking, if you introduce a capacitance manually without
considering the actual requirement, it may cause over compensation,
and lead to an arcing between the terminals of the equipment,
control device, or the source of power. This is a dangerous
situation. Even shunt capacitor across motors should be avoided if
there are more number of motors, and the system is on captive
generation. In such cases APFC (Automatic Power Factor Control)
relay is more reliable. Even with APFC, suppose the design is in
such a way that, it can be activated with generator source also.
APFC must be be very reliable and intelligent and capacitor banks
should have fine steps to accurately obtain the desired accurate
correction. Otherwise, similar situation of leading PF may be
created and the generator performance may be affected. So, I
conclude that even with APFC, try to include it in grid path only.
Please go
through the paper available from
here. |
|
Back |
|
What is the load limit insisted for HT-LT tariff? |
|
For new
consumers connected load permitted under LT may be limited to 100
kVA. But consumers existing as on 2nd March-05 may be permitted to
operate in LT up to a load of 150 kVA. |
|
|
Back |
|
What are the voltage limits insisted for different connected loads? |
|
Supply Voltage |
240
V |
415kV |
11kV |
22kV |
33
kV |
66
kV |
110
kV |
220
kV |
Max Connected Load |
5 kW |
100
kVA |
|
|
|
|
|
|
Max Contract Demand |
|
|
3000
kVA |
6000
kVA |
12000 kVA |
20000 kVA |
40000 kVA |
>40000 kVA |
|
|
Back |
|
In
case of multi storied building, what are the limits insisting for provision
of transformer? |
|
In
case of multistoried buildings having connected load below 50 kVA,
Licensee shall provide service connection from the LT line. For
loads of 50 kVA and above, connection shall be affected only after
installation of separate transformer of adequate capacity by the
owner/occupier.
In
case of Licensees other than KSEB (eg:- Kinfra, Technopark, etc.),
for multistoried buildings having several service connections with
more than 100 kVA connected load, connections can be extended at
Medium Voltage by providing bus ducts of adequate current carrying
capacity and complying with Indian Electricity Rules 1956 or new
rules framed as per provisions of the Act after installation of a
single transformer of adequate capacity by the Licensee. Tariff
applicable to such consumers shall be HT Tariff with appropriate
modifications regarding Transformer losses, after obtaining approval
of Kerala State Electricity Regulatory Commission. |
|
Back |
|
In case
of multi storied building consumers, what is the load limit for HT-LT
tariff? |
|
Even
in case of multi storied building consumers, the load limit for
HT-LT tariff is the same as explained above. |
|
Conditions to
avail HT common supply in a high rise apartment building may be explained. |
|
As
per KSEB Terms and Conditions of Supply, 2005, Clause
13(2)(b), "If common and essential loads in the building is 100 kVA
and above, separate transformer with HT metering arrangement shall
be installed exclusively for such loads".
Consider there are two buildings in the same premises. Let the
buildings are having the common and essential loads of say, 70kVA
each (So, total of 140kVA). The two buildings are physically
segregated but comes under a single builder. So, they may approach
with a single application (being the same premises and in future
there may be a single residence association to manage) to Electrical
Inspectorate and KSEB.
(a)
Consider, the common and essential loads are shared by both
buildings and there is only one transformer connection. If the total
common load exceeds 100kVA, then H T connection shall be insisted
for the common loads.
(b)
Consider two independent transformers are fed from a common 11kV
panel (1+2) and the common amenities of the two buildings are not at
all shared and each of them comes around say, 70kVA (so the total
>100kVA). In such a case, HT tariff common supply need not be
insisted.
(c)
Consider, the common and essential loads are not shared by the
buildings and there is only one transformer connection. In such a
case, I suggest you to care with the electrical design that two
exclusive different feeders with independent metering shall be taken
from the main switch board to feed the two sections. Otherwise, how
they can give you non-HT connection with a single metering
arrangement but connected load >100kVA? |
|
Explain AVR (Automatic
Voltage Regulation) |
|
AVR
(Automatic Voltage Regulation) is an electronic circuit which will
watch out the electricity output power from the generator supplied
to the load(s). Now if the load increases (for example) then there
will be more current to be drawn which will affect the RPM of the
generator then the frequency of the generator (RPM) will drop down.
The AVR in this case will increase the fuel (for example) to
increase the RPM of the generator so the frequency will stay fixed
(50 Hz for example). Also another possibility is to increase the
armature voltage and current to it will able to compensate the
voltage drop over the output lines. |
|
In which cases the outdoor transformer
installations are restricted? Also, in which cases the oil type transformer
installations are restricted? |
|
Out
door transformer installations are not permitted in corporation
areas and in the premises of residential buildings. In case of
commercial buildings in areas other than corporation areas, out door
transformer installations shall be permitted, keeping a minimum
distance of 6m from the building. Otherwise, in such a case there
shall be a fire resistant wall in between the transformer and the
building keeping a minimum distance of 1.5m both from the building
and the transformer.
Oil filled
transformers are not permitted inside residential/commercial
buildings. But, outside such buildings oil filled transformers shall
be permitted subject to certain conditions. |
|
Why transformers are rated in kVA? |
|
A
Transformer itself will not make any change to the system power
factor, since both inherent losses viz copper loss (depends on
current) and iron loss (depends on voltage) are independent of power
factor. So, transformers are rated in kVA. |
|
What is the condition to have light
circuit segregation in factory premises? |
|
Generally
for factories with medium voltage connection, the lighting circuit
need to be segregated and metered separately, the tariff being
different.
Where as,
factories with EHT/HT tariff connections, when the total
connected lighting load is less than or equal to 5% of the connected
load for power, it can be tapped off from the power mains without
segregation. When the above lighting load exceeds this limit, the
whole lighting load should be segregated and metered by a sub-meter
and lighting consumption in excess
over 10% of the bulk supply consumption for power shall be charged
at 7 paise extra per kWh for EHT and 25 paise per kWh for HT consumers.
But, industries engaged in software development technology and
tissue culture units need not segregate industrial load, lighting
load and load for air conditioners. No Penalty shall be levied by
the Board for non-segregation of the load by these units. However,
such consumer shall install static capacitors having ISI
certification to improve the power factor of the load of air
conditioners if any. |
|
How to calculate the voltage drop of a 3 run
cable, say 3Rx3.5x185 Sq.mm cable? |
|
A 3 run
cable represent 3 resistors in parallel, so its effective resistance
will be one third. Hence, the effective voltage drop also will be
one third. So, when you consider the 3 run cable as a single unit,
the voltage drop shall be one third of the usual value of a single
run cable. (say 0.37/3mV=0.123mV for 3x3.5x185 Sq. mm cable).
Otherwise, you may calculate the adequacy of a single run cable, by
taking the current as one third of the proposed feeder capacity.
Both methods must give you same value. |
|
What is RTCC (Remote Tap Change Circuit)? |
|
RTCC is
Remote Tap Change Circuit connected to OLTC (Over Load Tap Changer)
of Transformer through control cables. It raise & lower the voltage
as accordingly specified by controlling the motor drive in OLTC
electrically (and manually through Push Buttons) In RTCC an AVR
(Automatic Voltage Regulator) is fixed to maintain the output
voltage level (raise & lower) by controlling the motor.
"On
Load Tap Changer (OLTC)" means a device provided on high voltage
side of transformer, which is used for variation of voltage during
charged condition of the transformer.
"Off
Circuit Tap Changer (OCTC)" means a device provided on high
voltage side of transformer, which is used for variation of voltage
during OFF condition of the transformer. |
|
Percentage Impedance - basics? |
|
A transformer constitutes a self impedance to current flow from
source to load. Higher the impedance, the more voltage drop will
occur for a given load. If a fault occurs, its effect on the circuit
is lessened to the extend that transformer impedance increases. This
self impedance can be evaluated by a simple test.
The secondary terminals are short
circuited. A low voltage is then applied across the primary
terminals, and increased until the secondary current reaches the
rated current. The impedance is then the ratio of that primary
voltage to the rated voltage, multiplied by 100, which is called as
the percentage impedance of the transformer.
A
transformer's percent impedance is evaluated by a simple test. The
secondary terminals are short-circuited. A low voltage is then
applied to the primary terminals, and increased until the current
measured in the short-circuited secondary reaches the rated ampere
value. The impedance is then the ratio of that primary voltage to
the rated voltage; multiplying that by 100 gives the impedance in
percent.
The
impedance of the transformer is assumed as 5 %. Generally this is
for transformers up to 500 KVA. Above 500 KVA the impedance is
higher.
For
generators the impedance is much higher than that of the
transformers.
|
|
Why voltage
multiples of 11 is preferred? (eg:-
11kV, 110kV,
220kV, etc.)? |
|
With AC power systems,
a
factor was arrived at � relating the RMS value and the average
value, called Form Factor, which is the ratio of RMS value to the
Average value, which for a sinusoidal wave form was about 1.1. When
the voltage was to be transformed, it is easy to have a whole number
for the turns ratio of the transformer and hence all subsequent AC
voltages became multiples of 11.
|
|
List of materials - descending order of
Conductivity |
|
C l i c k h e r e |
|
Top |
Back |
|
Friends, if you find any
of the above explanations as not satisfactory, please mail me with your
valid suggestions.
Also, let us share
similar basic unnoticed queries. Please
Please join the Technical Discussions at the Forum -
Click here |